FY 18/19 Pavement Rehabilitation Project

The FY 18/19 Pavement Rehabilitation Project will begin on June 17, 2019 and should be completed sometime in July, weather permitting. (Construction Work Hours M-F from 7am to 4pm)

June 17- 20: Mobilization Period (field layout, tie off monuments and utilities, renotify affected residents/businesses, install BMPs and call for USA)
 
June 21 (begin cold-milling):
- Mariposa Ave. (between Center St. and PCH)
- Oregon St. (between Mariposa Ave. and Pine Ave.)
- California St. (between Mariposa Ave. and Pine Ave.)

June 24 (begin cold-milling):
- Center St. (between Maple Ave. and Grand Ave.)
- Nevada St. (from Mariposa Ave. to southern terminus)

June 24 (begin resurfacing):
- Mariposa Ave. (between California St. and PCH)
- Nevada St. (from Mariposa Ave. to southern terminus)
- Oregon St. (between Mariposa Ave. and Pine Ave.)
- California St. (between Mariposa Ave. and Pine Ave.)

June 25 (begin cold-milling):
- Maple Ave. (between Center St. and PCH)

June 25 (begin resurfacing):
- Center St. (between Mariposa Ave. and Grand Ave.)
- Mariposa Ave. (between Center St. and California St.)

June 26 (begin cold-milling):
- Maple Ave. (between Sheldon St. and Center St.)
- Center St. (between Imperial Ave. and Maple. Ave.)

June 26 (begin resurfacing):
- Maple Ave. (between Center St. and PCH)
- Center St. (between Maple Ave. and Mariposa Ave.)

June 27 (begin cold-milling):
- Cedar St. (between Imperial Ave. and Walnut Ave.)
- Walnut Ave. (between Cedar St. and Main St.)
- El Segundo Blvd. (between Aviation Blvd. and Isis Ave.)

June 27 (begin resurfacing):
- Center St. (between Imperial Ave. and Maple Ave.)
- Maple Ave. (between Sheldon St. and Center St.)

June 28 (begin resurfacing):
- Cedar St. (between Imperial Ave. and Walnut Ave.)
- Walnut Ave. (between Cedar St. and Main St.)
- El Segundo Blvd. (between Aviation Blvd. and Isis Ave.)


The project includes removal and replacement of top two inches roadway surface with new asphalt concrete, manhole and valve cover adjustments, pavement striping restoration and traffic loop restoration.

Local access to driveways will be maintained. The contractor will post "No Parking" signs in the work zone, in advance of the work being performed. We request that you refrain from running excess water in the gutters during the construction period.

For any questions or assistance, please contact:
1. Sebastian Rivas, Hardy & Harper Project Foreman - (714) 620-5548
2. Arianne Bola, City of El Segundo Project Manager - (310) 524-2364