The City's contractor, CJ Concrete Construction, Inc., will begin construction for the CDBG ADA Curb Ramp Installation Project next Wednesday, November 6, 2024.
They will remove and replace non-compliant curb ramps or install truncated domes on curb ramps.
Multiple project locations:
- Along W. Holly Ave. between Valley St. and Concord St.,
- Along W. Pine Ave. between Valley St. and Virginia St.
A location map is included with the City Notice of Imminent Construction --> available via this link.
Construction period and anticipated schedule:
- November 6, 2024, to December 20, 2024. Work hours will be Monday through Friday, 7:00 am to 4:00 pm.
- The schedule is subject to change due to material availability, weather, unforeseen circumstances, etc.
- Unless otherwise stated, ADA-compliant curb ramps will be installed at the intersections and corners listed below.
Week 1 - Nov. 6 to Nov. 8, 2024
- W. Pine Ave./Whiting St. – NW, NE, SW, SE corners
- W. Pine Ave./Virginia St. – NW, NE, SW
Week 2 - Nov. 12 to Nov. 15, 2024
- W. Pine Ave. /Loma Vista St. – NW, NE, SW
- W. Pine Ave./Valley St. – SW, SE
- W. Holly Ave./Valley St. – NE, SE corners
- W. Holly Ave./Loma Vista St. – NW, SW, SE
- W. Holly Ave./alley entrance between Whiting St. and Virginia St. – SW
- W. Holly Ave./Whiting St. – NW, NE, SW, SE
Week 3 - Nov. 18 to Nov. 24, 2024
- W. Holly Ave./alley entrance between Whiting St. and Virginia St. – NW, NE
- W. Holly Ave./alley entrance between Virginia St. and Concord St. – SE
- W. Holly Ave./Richmond St. – NW
- W. Holly Ave./Virginia St. – NE, SE